Set your time sheet submission approval workflow prior to any real time entry taking place.
Please note: Mixing your approval methods can make an administrative mess. If your team wants to change configurations after users have submitted live time sheets, follow these steps:
- Set a cut-off date for all time entries before the switch-over
- Ensure all time sheets in the previous process are approved
- Making the change in the Administration section
- Monitor any time sheet resubmissions very carefully
Which Time Sheet Approval option is right for you?
None (Auto-Approved Time Sheets)
- Approve all time entries immediately upon time sheet submission
- This is the easiest method unless your team will truly monitor and approve time sheets
By Time Sheet 1-Tier Approver Only
- Submitted time sheets require the users' designated Time Sheet Approvers' approval
- All time entries on that time sheet are approved or rejected as a complete record
Time Sheet 1-Tier PM Approver Only
- Submitted time sheets require one project manager per project for every project included in the time sheet
- Notifications are sent to all project managers for each project
- The first project manager approving the time entries for their project automatically approves all time entries for that project
- No further approval required by any other project managers for that same project
- All separate projects on the time sheet must be approved by one of the project managers in order for the time sheet to complete the approval process
- Any time entries on the time sheets which are not associated with projects are automatically approved (i.e. Company-level time entries)
By Time Sheets 2-Tier PM Approval & Final Approver
- Follow the same process for both the 1-Tier PM Approver Only followed by the 1-Tier Approver Only
- In other words, PMs will look at their individual project time entries first, then the final approver approves the entire time sheet
- The final approver process cannot take place until all projects have been approved through the project manager approval process