In some Project Management situations, smart schedulers like yourselves want the ability to designate a task as critical. Project Insight has previously identified critical tasks automatically because these tasks fall along the critical path. What if we want some tasks to be critical even if they're not along the critical path?
Simply right click somewhere in the non-link task line and go to Edit Task (full).
Once in the Edit Task (full), the new functionality here is the highlighted "Always Critical" checkbox.
May we also suggest, if critical tasks are of importance to you, to add the column which identifies critical tasks to your task list so you can easily identify them.
Your automatically and manually designated critical tasks will now be easily identified as a red exclamation point in the column.