This feature is an option on the Default Task Options under Project Settings. Enabling it will change the project schedule when actual dates entered by the resources differ from the scheduled dates entered by the project managers.
- This will only occur if the percent complete for a task is greater than 0
- The schedule will change without any PM intervention as resources update tasks
For example, no matter what the Scheduled Start/End Date for the task above, after the Actual Start/End Dates are generated, the Project Task View will show the updated Actual Dates.