Task Dependencies include the three following task relationships.
- Summary Task - The direct summary task within which this task is contained.
- Task Predecessors - All tasks which this task has specifically set as its direct predecessors.
- Task Successors - All tasks which have this task specifically set as a direct predecessor task.