Set categories for reporting particular categories of tasks beyond making them milestones.
For example, tasks which represent the go live date for new implementations could have a "Go Live" task type for reporting on the "Go Live" tasks across multiple projects.
Enable the TASK TYPES ADD-ON in PI administration:
Then hit the configure button:
The Task Type feature is most often used in conjunction with the rate flow function:
This rate flow is snipped from the bottom of a Contract.
Comments
4 comments
How do I find Task Type in the system to create options?
Thank you, Ricarda. I added additional information to this article because it wasn't very helpful.
You'll find your Task Type options in the Administration section under "Projects"
That was helpful. Just need to specify that the "Task Type" add-on needs to be added.
Thanks.
Gerard
Hi Gerard,
You are correct. We changed that in the recent months, so I will update the article.