Skip to main content

Intelligent scheduling

Comments

1 comment

  • Alex Roman

    Hi Olivia,

    In your scenario above, IF all tasks are linked with predecessor/successor relationship and if you change the duration of the task to match the done date the task was completed it would pull the other tasks. 

    Example

    Task 1 - ends on Feb. 15th 

    Task 2 - starts immediately after task 1 (if predecessor/successor relationship was set with Finish to Start) that would mean Task 2 would start Feb. 16th and according to your scenario above ends May 15th.

    Now if Task 1 ended instead on 14th, the user would have to change the duration to one day less and it would pull all other tasks in by 1 day, however if the user does not changed the duration it will remain with the same dates.

    0

Please sign in to leave a comment.

Powered by Zendesk