What report can show me how much work is planned in any given month?
Ideally I’d like this to work similar to a Resource Report where the first rollup is Project so I can see all of the hours committed to “Project X” for the month of August, and then drill in to see the Resources who have work hours committed in the month of August.
0
-
Official comment
Hi Olivia,
The resource report is a great report, another report that can show what work was planned if you are referring to Work Hours is the Task Resource report that allows to group by various items such as Projects, then Resource and also filter on incomplete Tasks.