Tentative Dates
It would be great to set dates as tentative as you gather information for the project. Currently setting up a new project with a number of staff involved and some dates are actual from staff others I have had to estimate before presenting to staff for confirmation. When I present difficult to know if the dates entered are actual as provided by staff or my estimates
-
Official comment
Thank you for your feature suggestion. One thing you can do right now is to add a user-defined field for the task item as an identifier for tasks with estimated dates. Set the new data field as a filter and you can display only those tasks in lists and reports. The task list will then allow you to only display the estimated tasks for easy updates as you gather more information to nail those dates down.