Adding Hours for Team Member
I'm the Project Manager for a Project that is almost complete. I have a key resource who did most of the work and has now left the project (and the company)... I need to add his hours to complete our client billing process.
How can I add his hours?
0
-
Official comment
A project manager can add hours on behalf of a resource in each task's detail screen. There is a drop down to select between the different resources you wish to add time for:
If you do not see his/her name, make sure s/he is assigned to the task and a project resource. S/he does not need to be an active resource.